We started a projected schedule towards the end of September of 2017.  The objective is to build a rolling chassis, and steering Ultra4 race car by the middle of June 2018.  The team compiled a list of everything they thought that would be necessary to build a buggy.  First the team picked out key categories of the build, most of which were then sub-divided further; for Example: the engine has its own category, with subcategories of rebuilding, tuning, and ordering parts.  Next the team decided how long they thought it would take to complete each section of the build.  We estimated lead and manufacturing times by referencing similar parts and situations that gave more accurate estimates.

The team started the schedule on a whiteboard and it progressed from there.  There have been a few amendments to the schedule including entering the projected times into Microsoft Project, and an update to the schedule for each term.

Estimating material and machinery allocation times has been a learning curve.  The necessary machines have all been attained by the start of each project.  Items such as vertical drills, chop saws, drills, grinders, and notchers have all been gathered beforehand.  The team has been diligent in keeping ahead on what they may need. However, it is the small everyday items that were not as obvious to pre-purchase, such as the proper PPE, or something as simple as kerosene for the shop heater.  These items were bought on the spot as needed.  The metal for the shop was purchased at a discount from a local metal supplier.  All of the metal for the project was purchased and bought at the same time.  KC also purchased extra tube in foresight of mistakes.  Even with proper planning we found that we may still need a few pieces of metal.

To manage the team members, they were all assigned according to skill level to different subsections of the buggy build.  It was difficult to manage people’s time because there have been multiple terms of classes, and schedules were constantly changing.  The team members worked independently conducting research on the subsections.  A lot of the physical build need KC or James Wray’s attendance because their skills were the most proficient with the tube-notcher and welding.  They have also had previous experience in fabrication.

 

It will be crucial to culminate the skills of the different team members to complete the project in the necessary time and budget.  There is an understanding that the time and cost are major factors in the project management triangle.  The only thing we can change is the scope.  If necessary we can scale back the scope in hopes to contribute a project that meets the requirements and gives us skills in the engineering environment.


Note: Link to Gantt Chart in Microsoft Project Format

Task Mode Task Name Duration Start Finish Predecessors Baseline1 Estimated Start Baseline Estimated Finish Baseline Estimated Duration
Auto Scheduled Ultra4 4800 132 days? Thu 10/5/17 Fri 4/6/18 Wed 11/1/17 Mon 4/9/18 114 days
Auto Scheduled    Frame Bench 94 days? Wed 11/1/17 Mon 3/12/18 Wed 11/1/17 Wed 1/31/18 66 days
Auto Scheduled       Design/Size 10 days Wed 11/1/17 Tue 11/14/17 Wed 11/1/17 Mon 11/6/17 4 days
Auto Scheduled       Jigs 3 days Sat 1/27/18 Wed 1/31/18 Sat 1/27/18 Wed 1/31/18 3 days
Auto Scheduled       Jig Round 2 1 day? Mon 3/12/18 Mon 3/12/18 NA NA 0 days
Auto Scheduled       Get Material 2 days Thu 11/16/17 Fri 11/17/17 6 Thu 12/21/17 Fri 12/22/17 2 days
Auto Scheduled       Build 7 days Fri 12/1/17 Mon 12/11/17 9 Wed 11/22/17 Thu 11/30/17 7 days
Auto Scheduled    Chassis 96 days? Tue 10/31/17 Tue 3/13/18 5 Thu 11/30/17 Thu 2/1/18 0 days
Auto Scheduled       Wheel Base 2 days Tue 10/31/17 Wed 11/1/17 Thu 11/30/17 Fri 12/1/17 0 days
Auto Scheduled       Seats 1 day Thu 11/30/17 Thu 11/30/17 Thu 11/30/17 Thu 11/30/17 0 days
Auto Scheduled       Maintenance 2 days Thu 11/30/17 Fri 12/1/17 Thu 11/30/17 Fri 12/1/17 0 days
Auto Scheduled       Model 1 day Thu 12/14/17 Thu 12/14/17 Thu 11/30/17 Wed 12/6/17 0 days
Auto Scheduled       Order Tube 2 days Mon 2/5/18 Tue 2/6/18 Sat 12/9/17 Tue 12/12/17 0 days
Auto Scheduled       Bend 1 day Tue 2/6/18 Tue 3/13/18 16 Wed 12/13/17 Tue 12/19/17 0 days
Auto Scheduled       Engine/Trans. Mounts 2 days Sat 12/23/17 Tue 3/13/18 20 Sat 12/23/17 Thu 2/1/18 0 days
Manually Scheduled       Notch 1 day? Mon 2/5/18 Mon 2/5/18 17 Thu 12/21/17 Thu 12/21/17 0 days
Auto Scheduled          Weld 1 day? Thu 12/21/17 Mon 2/5/18 Thu 12/21/17 Thu 12/21/17 0 days
Auto Scheduled    Engine/Transmission 110 days Thu 10/5/17 Wed 3/7/18 Wed 11/1/17 Fri 3/2/18 0 days
Auto Scheduled       Teardown/Inspect 1 day Thu 10/5/17 Thu 10/5/17 Wed 11/1/17 Wed 11/1/17 0 days
Auto Scheduled       Rebuild 2 days Thu 11/16/17 Fri 11/17/17 25 Thu 11/16/17 Fri 11/17/17 0 days
Auto Scheduled       CNC Port and Polish 2 wks Thu 2/22/18 Wed 3/7/18 NA NA 0 days
Auto Scheduled       Order Parts 10 days Thu 11/30/17 Wed 12/13/17 22 Thu 11/2/17 Wed 11/15/17 0 days
Auto Scheduled       Fix Trans Leak 1 day Sat 11/18/17 Mon 11/20/17 23 Sat 11/18/17 Mon 11/20/17 0 days
Auto Scheduled       Torque Converter 1 day Tue 11/21/17 Tue 11/21/17 26 Tue 11/21/17 Tue 11/21/17 0 days
Auto Scheduled       Installation 2 days Thu 3/1/18 Fri 3/2/18 Thu 3/1/18 Fri 3/2/18 0 days
Auto Scheduled    Brakes 58 days Sat 12/23/17 Wed 3/14/18 11 Sat 12/23/17 Fri 1/5/18 0 days
Auto Scheduled       Pull Drums 1 day Sat 12/23/17 Mon 12/25/17 Sat 12/23/17 Mon 12/25/17 0 days
Auto Scheduled       Disk Conversion 2 days Wed 12/27/17 Thu 12/28/17 Wed 12/27/17 Thu 12/28/17 0 days
Auto Scheduled       Design 2 days Thu 3/1/18 Wed 3/14/18 Sun 12/24/17 Mon 12/25/17 0 days
Auto Scheduled       Order 1 day Fri 12/29/17 Fri 12/29/17 32 Fri 12/29/17 Fri 12/29/17 0 days
Auto Scheduled       Mount 1 day Mon 1/1/18 Mon 1/1/18 33 Mon 1/1/18 Mon 1/1/18 0 days
Auto Scheduled       Plum 1 day Tue 1/2/18 Tue 1/2/18 34 Tue 1/2/18 Tue 1/2/18 0 days
Auto Scheduled       Parking Brake 1 day Thu 1/4/18 Thu 1/4/18 35 Thu 1/4/18 Thu 1/4/18 0 days
Auto Scheduled       Manual 1 day Fri 1/5/18 Fri 1/5/18 36 Fri 1/5/18 Fri 1/5/18 0 days
Auto Scheduled    Cooling 10 days Fri 3/2/18 Thu 3/15/18 Fri 3/2/18 Thu 3/15/18 0 days
Auto Scheduled       Design 2 days Fri 3/2/18 Mon 3/5/18 Fri 3/2/18 Mon 3/5/18 0 days
Auto Scheduled       Fans 2 days Fri 3/9/18 Mon 3/12/18 Fri 3/9/18 Mon 3/12/18 0 days
Auto Scheduled       Order Parts 2 days Tue 3/6/18 Wed 3/7/18 39 Tue 3/6/18 Wed 3/7/18 0 days
Auto Scheduled       Plum 2 days Tue 3/13/18 Wed 3/14/18 Tue 3/13/18 Wed 3/14/18 0 days
Auto Scheduled       Torque Converter Stall Speed 1 day Thu 3/15/18 Thu 3/15/18 Thu 3/15/18 Thu 3/15/18 0 days
Auto Scheduled    Axles 23 days Tue 2/6/18 Thu 3/8/18 53 Thu 2/1/18 Tue 2/13/18 0 days
Auto Scheduled       Design Trusses 2 days Wed 3/7/18 Thu 3/8/18 Thu 2/1/18 Fri 2/2/18 0 days
Auto Scheduled       Clean 3 days Thu 3/1/18 Mon 3/5/18 Sat 2/3/18 Mon 2/5/18 0 days
Auto Scheduled       Re-Gear (end) 1 day Tue 2/6/18 Tue 2/6/18 Tue 2/6/18 Tue 2/6/18 0 days
Auto Scheduled       Re-Build (end) 1 day Wed 2/7/18 Wed 2/7/18 Wed 2/7/18 Wed 2/7/18 0 days
Auto Scheduled       Long Adapter (end) 1 day Thu 2/8/18 Thu 2/8/18 Thu 2/8/18 Thu 2/8/18 0 days
Auto Scheduled       Weld 1 day Tue 2/13/18 Tue 2/13/18 52 Tue 2/13/18 Tue 2/13/18 0 days
Auto Scheduled       Brackets 1 day Fri 2/9/18 Fri 2/9/18 Fri 2/9/18 Fri 2/9/18 0 days
Auto Scheduled       Fab Truss 1 day Sat 2/10/18 Mon 2/12/18 Sat 2/10/18 Mon 2/12/18 0 days
Auto Scheduled    Suspension 12 days Wed 2/14/18 Thu 3/1/18 11 Wed 2/14/18 Thu 3/1/18 0 days
Auto Scheduled       Design 5 days Wed 2/14/18 Tue 2/20/18 Wed 2/14/18 Tue 2/20/18 0 days
Auto Scheduled       Trailing Arm Design 3 days Wed 2/21/18 Fri 2/23/18 Wed 2/21/18 Fri 2/23/18 0 days
Auto Scheduled       Trailing Arm Build 2 days Sat 2/24/18 Tue 2/27/18 Sat 2/24/18 Tue 2/27/18 0 days
Auto Scheduled       Front Arm Design 2 days Wed 2/28/18 Thu 3/1/18 Wed 2/28/18 Thu 3/1/18 0 days
Auto Scheduled    Wiring 87 days Thu 11/30/17 Fri 3/30/18 44 Wed 3/14/18 Fri 3/30/18 0 days
Auto Scheduled       Engine Harness Research 7 days Thu 11/30/17 Fri 3/16/18 Wed 3/14/18 Thu 3/22/18 0 days
Auto Scheduled       Gauges 1 day Fri 3/23/18 Fri 3/23/18 Fri 3/23/18 Fri 3/23/18 0 days
Auto Scheduled       Off-Road Lights 1 day Sat 3/24/18 Mon 3/26/18 Sat 3/24/18 Mon 3/26/18 0 days
Auto Scheduled       Winch 1 day Tue 3/27/18 Tue 3/27/18 61 Tue 3/27/18 Tue 3/27/18 0 days
Auto Scheduled       Install 1 day Wed 3/28/18 Wed 3/28/18 62 Wed 3/28/18 Wed 3/28/18 0 days
Auto Scheduled       Cooling Fans 1 day Thu 3/29/18 Thu 3/29/18 63 Thu 3/29/18 Thu 3/29/18 0 days
Auto Scheduled       Fuel pumps 1 day Fri 3/30/18 Fri 3/30/18 64 Fri 3/30/18 Fri 3/30/18 0 days
Auto Scheduled    Fuel System 63 days Wed 1/10/18 Fri 4/6/18 58 Sun 4/1/18 Mon 4/9/18 0 days
Auto Scheduled       Design 2 days Wed 1/10/18 Mon 4/2/18 Sun 4/1/18 Tue 4/3/18 0 days
Auto Scheduled       Order 1 day Wed 4/4/18 Wed 4/4/18 67 Wed 4/4/18 Wed 4/4/18 0 days
Auto Scheduled       Plum 2 days Thu 4/5/18 Fri 4/6/18 68 Thu 4/5/18 Fri 4/6/18 0 days
Auto Scheduled       Cell 1 day Fri 3/9/18 Fri 3/9/18 Sat 4/7/18 Mon 4/9/18 0 days
Auto Scheduled    Steering 98 days? Wed 11/1/17 Fri 3/16/18 NA NA 0 days
Auto Scheduled       Design 10 days? Mon 3/5/18 Fri 3/16/18 NA NA 0 days
Auto Scheduled       Order Parts 1 day? Wed 11/1/17 Wed 11/1/17 NA NA 0 days